There are 6 results

Search results

End of week 28 and 29 Update

Posted by: Network Improvements Team Posted on: 26 April 2021 09:34
Categories: April 2021

Constructing carriageway up to binder course along new alignment.

End of week 27

Posted by: Network Improvements Team Posted on: 12 April 2021 10:13
Categories: April 2021

Northbound carriageway gullies have been constructed and street lighting being installed.

End of week 26

Posted by: Network Improvements Team Posted on: 06 April 2021 11:04
Categories: April 2021

Kerb line on northbound carriageway completed.

End of week 20

Posted by: Network Improvements Team Posted on: 22 February 2021 13:15
Categories: February 2021

New road alignment along A339 kerbed and drainage works.

End of week 19

Posted by: Network Improvements Team Posted on: 12 February 2021 10:26
Categories: February 2021

More utility diversions and progress on upgrading drainage on the A339.

January 2021 Update - End of week 17

Posted by: Network Improvements Team Posted on: 03 February 2021 11:37
Categories: February 2021

This month on site utility diversions have started.