End of Week 53

Posted by: Network Improvements Team Posted on: 11 October 2021 11:00
Categories: October 2021

There is no summary for this End of Week 53 blog article

UPDATE - Road Closed - Saturday 9 October through to Sunday 10 October 2021

Posted by: Network Improvements Team Posted on: 08 October 2021 09:05
Categories: October 2021

The closure will be permitted from 7am on Saturday 9 October through to 9pm on Sunday 10 October 2021.

End of Week 51 and 52

Posted by: Network Improvements Team Posted on: 04 October 2021 10:10
Categories: October 2021

The previous weeks have seen the protective barriers moved to the middle of the carriageway.

End of week 33

Posted by: Network Improvements Team Posted on: 24 May 2021 09:57
Categories: May 2021

Southbound verge works continue with drainage and excavations.

End of week 32

Posted by: Network Improvements Team Posted on: 18 May 2021 10:13
Categories: May 2021

Lane closure has been moved to the southbound carriageway.

End of week 31

Posted by: Network Improvements Team Posted on: 10 May 2021 10:45
Categories: May 2021

Laying of binder course in widened carriageway.

End of week 30

Posted by: Network Improvements Team Posted on: 04 May 2021 10:55
Categories: May 2021

Final bits of carriageway widening around Household Waste Recycling Centre

End of week 24 and 25

Posted by: Network Improvements Team Posted on: 30 March 2021 09:58
Categories: March 2021

Drainage installation on A339.

End of week 23

Posted by: Network Improvements Team Posted on: 15 March 2021 09:49
Categories: March 2021

Progress with reinstatement around Household Waste Recycling Centre.

End of week 22

Posted by: Network Improvements Team Posted on: 08 March 2021 11:05
Categories: March 2021

Progress with drainage works and reinstatement.