End of week 30

Posted by: Network Improvements Team Posted on: 04 May 2021 10:55
Categories: May 2021

Final bits of carriageway widening around Household Waste Recycling Centre

End of week 28 and 29 Update

Posted by: Network Improvements Team Posted on: 26 April 2021 09:34
Categories: April 2021

Constructing carriageway up to binder course along new alignment.

End of week 27

Posted by: Network Improvements Team Posted on: 12 April 2021 10:13
Categories: April 2021

Northbound carriageway gullies have been constructed and street lighting being installed.

End of week 26

Posted by: Network Improvements Team Posted on: 06 April 2021 11:04
Categories: April 2021

Kerb line on northbound carriageway completed.

End of week 24 and 25

Posted by: Network Improvements Team Posted on: 30 March 2021 09:58
Categories: March 2021

Drainage installation on A339.

End of week 23

Posted by: Network Improvements Team Posted on: 15 March 2021 09:49
Categories: March 2021

Progress with reinstatement around Household Waste Recycling Centre.

End of week 22

Posted by: Network Improvements Team Posted on: 08 March 2021 11:05
Categories: March 2021

Progress with drainage works and reinstatement.

End of week 21

Posted by: Network Improvements Team Posted on: 01 March 2021 14:40
Categories: March 2021

Northbound utility diversions complete and continuing with drainage works.

End of week 20

Posted by: Network Improvements Team Posted on: 22 February 2021 13:15
Categories: February 2021

New road alignment along A339 kerbed and drainage works.

End of week 19

Posted by: Network Improvements Team Posted on: 12 February 2021 10:26
Categories: February 2021

More utility diversions and progress on upgrading drainage on the A339.