End of week 41
Continued progress with utilities and pavement construction.
on
19 July 2021
10:52
Last week, the remaining utilities continued being worked on, with new inspection chambers being constructed where needed. Due to their location, they can be fairly substantial, and in the example below will be constructed using concrete around this form work.
Other smaller chambers have also been constructed using pre-cast concrete rings, similar to the drainage installed previously. The use of both styles depends on their intended purpose after construction.
More sub-base has also been laid last week, in preparation for the tarmac layers to be laid once the final stages of the utilities have been completed.
Activities on site next week:
- Continuing to construct the new carriageway pavement and new footpath.