Continued progress on pavement construction.

Posted by: Network Improvements Team on 15 September 2021 11:22

Last week, more progress was made laying the binder course over various locations on site. The northern most section around the existing bus stop was laid in preparation for the surface course.

Week 49 footway binder

The new central islands, which will serve as a new signalised crossing across the A339 and house the traffic lights, have also been kerbed. The access chambers for the traffic light infrastructure have also been installed, allowing for their installation in the near future. 

Week 49 central island

Activities on site next week:

  • Complete laying material up to binder course, in preparation for final surface course
  • Pulling of cables for traffic light infrastructure